New Home Construction Schedule

New Home Construction Schedule

How long does it take to build a house? Scroll down this page to see an example of a typical construction schedule for a large (6,000 sq. ft.) custom home. It includes most, but not all, of the activities involved in the process of building a new house in most parts of the country. Sample construction draws have been included for reference purposes, although individual lenders & mortgage companies will most likely have their own draw schedules.

Notice that because construction draws from the lender typically follow the completion of various phases, or milestones, the cash flow on a project can be very irregular. While the money flowing out of a construction company; for employee salaries, benefits, office space, vehicles, insurance, equipment and other company expenses, typically occurs on a regular calendar based timeline, the money used to pay these expenses follows an event driven schedule. Therefore, besides the "normal" unplanned events that can affect the progress of a home building project, it is not uncommon for home builders to rearrange construction schedules in order to gain access to draw money so that they are able to pay subcontractors and suppliers in a timely manner. By the way, this is generally a good thing (provided you have an honest builder) because subcontractors tend to follow the money and happy subs are almost always preferable to unhappy ones:-)

Will your house take this long to build?

Probably not; most home building projects will take less time, but some will take even more. For example, the timeline for a smaller house, with few options and less detailed finishes, which has been built many times before by professional builders, might be as short as 8 to 12 weeks. However, 6 to 9 months from start to finish is probably a more realistic average (average is not a good word for a typical homeowner). While a larger house, with more options, custom features, fancier finishes, and more owner involvement -- especially if the owner has little construction experience -- may very well take 1 1/2 to 2 years to complete. Then again, if you build your own house, and make the common mistake of moving in before every last detail is finished, well, you might be looking at decades instead of months or years --- I speak from experience, but it's just a little trim in the powder room, and a short piece of baseboard behind the master bath door, and a small piece of molding in the hallway linen closet, and....

The actual schedule of completion for your specific project will vary based upon many factors including, but not limited to, size and degree of difficulty of the structure, site and weather conditions, material and contractor availability, crew sizes, effective scheduling and communication, the knowledge and experience of those managing the project, and perhaps most significantly, the number, timeliness, and complexity of the changes you will inevitably make to the original contract after construction has already begun.

 

ID

Outline Number

Name

Duration

Predecessors

Start

Finish

1

1

Contracts

0.00d

.

   

2

1.1

__Supply Lot Sale Agreement

0.00d

.

   

3

1.2

__Supply Construction Agreement

0.00d

.

   

4

1.3

__Supply Contract Plans

0.00d

3

   

5

1.4

__Supply Contract Specifications

0.00d

3

   

6

1.5

__Supply Contract Site Plan

0.00d

3

   

7

1.6

__Secure Financing

0.00d

.

   

8

1.7

__Construction Loan Settlement

0.00d

.

   

9

2

Document Review & Revision

25.00d

.

   

10

2.1

__Review & Finalize Plans

15.00d

4

   

11

2.2

__Review & Finalize Specifications

20.00d

5

   

12

2.3

__Review & Finalize Site Plan

1.00d

6,10

   

13

2.4

__Print Construction Drawings

5.00d

10,11,12

   

14

2.5

__Approve Revised Plans

0.00d

13

   

15

2.6

__Approve Revised Specifications

0.00d

13

   

16

2.7

__Approve Revised Site Plan

0.00d

13

   

17

3

Bids & Contracts

24.00d

.

   

18

3.1

__Make Copies of Plans

3.00d

14

   

19

3.2

__Make Copies of Specifications

2.00d

15

   

20

3.3

__Distribute Plans & Specifications

1.00d

18,19

   

21

3.4

__Receive Bids

10.00d

20

   

22

3.5

__Review Bids

5.00d

.

   

25

3.6

__Execute Subcontractor Agreements

5.00d

23

   

26

4

Grading & Building Permits

17.00d

.

   

27

4.1

__Schedule lot stake-out

1.00d

13

   

28

4.2

__Stake lot

1.00d

27FS+3d

   

29

4.3

__File Grading Permit Application

1.00d

16

   

30

4.4

__File Building Permit Application

3.00d

14,15,16

   

31

4.5

__Post Lot Identification

1.00d

28,29,30

   

32

4.6

__Meet Sed. Control Insp.

1.00d

29FS+2d,28,31

   

33

4.7

__Walk Lot w/ Owner

1.00d

32

   

34

4.8

__Install Construction Entrance

1.00d

32,33

   

35

4.9

__Install Sediment Controls

2.00d

32,33

   

36

4.10

__Sediment Control Insp.

1.00d

34,35

   

37

4.11

__Grading Permit Issued

1.00d

36

   

38

4.12

__Permit Process

10.00d

30

   

39

4.13

__Building Permit Approved

1.00d

38,37

   

40

4.14

__Pay Permit Fees and Excise Taxes

1.00d

39FS+2d

   

41

4.15

__Building Permit Issued

0.00d

40

   

42

5

Site Work

7.00d

.

   

43

5.1

__Clear Lot

3.00d

37

   

44

5.2

__Strip Topsoil & Stockpile

1.00d

43

   

45

5.3

__Stake Lot for Excavation

1.00d

43

   

46

5.4

__Rough grade lot

1.00d

43,45

   

47

5.5

__Excavate for foundation

2.00d

39,45,43,46

   

48

6

Foundation

24.00d

.

   

49

6.1

__Layout footings

1.00d

47

   

50

6.2

__Dig Footings & Install Reinforcing

1.00d

49

   

51

6.3

__Footing Inspection

0.00d

50

   

52

6.4

__Pour footings

1.00d

51

   

53

6.5

__Pin Footings

1.00d

52

   

54

6.6

__Stock Block, Mortar, Sand

1.00d

53

   

55

6.7

__Build Block Foundation

15.00d

53,54

   

56

6.8

__Foundation Certification

0.00d

55

   

57

6.9

__Draw #1 (Location Survey)

0.00d

56

   

58

6.10

__Fill Block Cores w/ Concrete

1.00d

55

   

59

6.11

__Steel Delivery

1.00d

58

   

60

6.12

__Set Lintels, Bolts, Cap Block

2.00d

59

   

61

6.13

__Lumber Delivery

1.00d

58

   

62

6.14

__Waterproofing and Drain Tile

1.00d

61

   

63

7

Rough Carpentry

44.00d

.

   

64

7.1

__Set Steel

1.00d

60

   

65

7.2

__1st Floor Deck Framing

4.00d

64

   

66

7.3

__1st Floor Wall Framing

4.00d

65

   

67

7.4

__Draw #2 (First Floor Deck)

0.00d

66

   

68

7.5

__2nd Floor Deck Framing

2.00d

67

   

69

7.6

__Draw #3 (Second Floor Deck)

0.00d

68

   

70

7.7

__2nd Floor Wall Framing

3.00d

69

   

71

7.8

__Set Roof Trusses

2.00d

70

   

72

7.9

__Frame Roof

7.00d

71

   

73

7.10

__Install Roof Plywood

5.00d

72

   

74

7.11

__Install Windows & Doors

2.00d

73,111

   

75

7.12

__Frame Basement

3.00d

72,81

   

76

7.13

__Frame Basement Bulkheads

2.00d

75,87,93

   

77

8

Concrete Slabs

8.00d

.

   

78

8.1

__Basement Slab Preparation

2.00d

65,91

   

79

8.2

__Termite Treatment Basement Slab

1.00d

78

   

80

8.3

__Slab Inspection

1.00d

79

   

81

8.4

__Pour Basement Slab

1.00d

80

   

82

8.5

__Prep Garage Slab

1.00d

81

   

83

8.6

__Termite Treatment Garage Slab

1.00d

82

   

84

8.7

__Pour Garage Slab

1.00d

83

   

85

9

H.V.A.C.

17.00d

.

   

86

9.1

__HVAC Layout & Measure

1.00d

72

   

87

9.2

__HVAC Rough-in

5.00d

86,111

   

88

9.3

__HVAC Set Indoor Units

2.00d

81,87

   

89

9.4

__HVAC Temporary Heat

2.00d

88

   

90

10

Plumbing Rough-in

37.00d

.

   

91

10.1

__Plumbing Sub-slab

2.00d

65

   

92

10.2

__Plumbing Layout

1.00d

91,87

   

93

10.3

__Plumbing rough-in

5.00d

92

   

94

11

__Plumbing Sub-slab Inspection

0.00d

91

   

95

12

__Plumbing Rough-in Inspection

0.00d

93

   

96

13

Electric Rough-in

19.00d

.

   

97

13.1

__Set Electric Boxes

2.00d

74

   

98

13.2

__Install Electric Service Panel

2.00d

97

   

99

13.3

__Electrical Walk-through

1.00d

98

   

100

13.4

__Electrical Rough-wire

14.00d

99

   

101

14

Specialty Rough-ins

5.00d

.

   

102

14.1

__Central Vacuum Rough-in

5.00d

100

   

103

14.2

__Alarm System Rough-in

5.00d

100

   

104

14.3

__Telephone System Rough-in

5.00d

100

   

105

14.4

__Television System Rough-in

5.00d

100

   

106

14.5

__Audio Visual Rough-in

5.00d

100

   

107

15

__ Electrical inspection

0.00d

96,101

   

108

16

Draw #5 (Rough-ins complete)

0.00d

95,107

   

109

17

Framing Inspection

0.00d

95FS+1d,107FS+1d

   

110

18

Roofing

68.00d

.

   

111

18.1

__Roofing Paper Installed

3.00d

73

   

112

18.2

__Draw #4 (Roof, windows, doors)

0.00d

74,111

   

113

18.3

__Stock Roof Shingles

1.00d

112

   

114

18.4

__Install Roof Shingles

7.00d

113,119

   

115

19

Exterior Finishes

56.00d

.

   

116

19.1

__Siding

3.00d

74

   

117

19.2

__Exterior Trim

7.00d

116

   

118

19.3

__Brick Arch Forms

1.00d

117

   

119

19.4

__Brick Veneer

45.00d

118

   

120

20

Insulation

5.00d

.

   

121

20.1

__Caulk & Air Seal

1.00d

109

   

122

20.2

__Draft & Fire Stop

1.00d

121

   

123

20.3

__Batt Insulation

3.00d

121,122

   

124

21

Insulation Inspection

0.00d

123,120

   

125

22

BGE Energy Wise Inspection

0.00d

124

   

126

23

Drywall

26.00d

.

   

127

23.1

__Stock Drywall

1.00d

124

   

128

23.2

__Hang Drywall

5.00d

127

   

129

23.3

__Remove Scrap Drywall

1.00d

128

   

130

23.4

__Tape and Finish Drywall

15.00d

128,129

   

131

23.5

__Sand Drywall

1.00d

130

   

132

23.6

__Drywall Point-up

3.00d

131

   

133

24

Draw #6 (Insulation & drywall applied)

0.00d

128,126

   

134

25

Floor Finishes

76.00d

.

   

135

25.1

__Ceramic Tile

15.00d

142

   

136

25.2

__Install Hardwood Floor

4.00d

146

   

137

25.3

__Sand, Stain, Seal Hardwood

5.00d

196

   

138

25.4

__Install Carpet

4.00d

137

   

139

25.5

__Final Coat Hardwood

2.00d

196

   

140

26

Paint

59.00d

.

   

141

26.1

__Prep Drywall for Prime Coat

2.00d

131

   

142

26.2

__Prime Paint Drywall

2.00d

141

   

143

26.3

__Prep Trim for Prime Coat

2.00d

142,152

   

144

26.4

__Prime Trim

2.00d

143

   

145

26.5

__Finish Coat Trim

10.00d

144,156

   

146

26.6

__Finish Coat Drywall

14.00d

145,132

   

147

26.7

__Caulk Exterior Windows & Doors

1.00d

146,117

   

148

26.8

__Finish Coat Exterior Trim & Siding

1.00d

147

   

149

27

Draw #7 (Roofing, masonry, siding)

0.00d

114,157

   

150

28

Interior Trim

29.00d

.

   

151

28.1

__Interior Trim Delivery

1.00d

142

   

152

28.2

__Install Interior Doors

5.00d

151

   

153

28.3

__Install Interior Trim

15.00d

152

   

154

28.4

__Install Cabinetry

5.00d

153

   

155

28.5

__Install Appliances

1.00d

154

   

156

28.6

__1st Punch-out Interior Trim

2.00d

155,144

   

157

29

H.V.A.C. Trim

1.00d

140

   

158

29.1

__Install Grills & Registers for Paint

1.00d

131

   

159

29.2

__Set Outdoor Units

1.00d

165

   

160

30

Plumbing Trim

5.00d

.

   

161

30.1

__Set Fixtures

4.00d

135,136,146,154

   

162

30.2

__Connect Appliances

1.00d

161

   

163

31

__Final Plumbing Inspection

0.00d

160

   

164

32

Exterior Landscaping

32.00d

.

   

165

32.1

__Rough Final Grade

1.00d

119

   

166

32.2

__Patios

7.00d

165,119

   

167

32.3

__Porches

5.00d

166,119

   

168

32.4

__Sidewalks

7.00d

167,119

   

169

32.5

__Decks

7.00d

168,119

   

170

32.6

__Driveways

2.00d

165,169

   

171

32.7

__Final Grade and Seed

3.00d

170,166,167,168

   

172

33

Electrical Final Trim

160.00d

.

   

173

33.1

__Switch & Plug

2.00d

142,100

   

174

33.2

__Install Fixtures

1.00d

.

   

175

33.3

__Connect Appliances

1.00d

.

   

176

34

Hardware

12.00d

.

   

177

34.1

__Door Hardware

2.00d

145,146

   

178

34.2

__Bath Hardware

2.00d

145,146

   

179

34.3

__Mirrors

5.00d

178

   

180

34.4

__Shower Doors

10.00d

178

   

181

35

Draw #8 (Prime paint, cabinets, doors)

0.00d

142,152,154

   

182

36

Draw #9 (Trim, furnace, hrdwd, tile, rails)

0.00d

153,181

   

183

37

Draw #10 (Plumbing & elec. trim, final paint)

0.00d

146,182

   

184

38

Final Building Inspection

0.00d

183

   

185

39

Use & Occupancy Certificate

0.00d

184FS+3d

   

186

40

First Walk-thru

0.00d

185

   

187

41

Draw #11 (Final payment per contract)

0.00d

186

   

188

42

Final Punch-out

9.00d

.

   

189

42.1

__Punch Out Walk-thru List

4.00d

186

   

190

42.2

__Trim and Adjust Doors

2.00d

184,189

   

191

42.3

__Paint Touch-up

3.00d

190

   

192

43

Cleaning

14.00d

.

   

193

43.1

__Windows

3.00d

145,146

   

194

43.2

__Rough Clean

3.00d

193

   

195

43.3

__Final Clean

2.00d

176,188

   

196

44

Final Walk-through

0.00d

187,188,192

   

197

45

Move-in

0.00d

196FS+1d